ASSUMPTIONS

ASSUMPTIONS

In sequencing problems, the following assumptions are made :-

i.            All machines can process only one job at a time.
ii.            No time is wasted in shifting a job from one machine to other.
iii.            Processing time of job on a machine has no relation with the order in which the job is processed.
iv.            All machines have different capability and capacity.
v.            All jobs are ready for processing.
vi.            Each job when put on the machine is completed.
vii.            All jobs are processed in specified order as soon as possible.